17th Annual Student Management Competition Preliminary Problem Statement for Commercial Division Fall 2009The project
is a 39,000 square foot, three (3) story office building being built as a new
corporate office for a national architectural firm.
This new facility will be located in a midtown development in an average
size Midwestern city. The
architectural owner will require this construction, when completed, be able to
achieve a LEED Gold Certification according to the USGBC.
The delivery method chosen for this project is CM at Risk.
The
building structure is masonry bearing, metal decking and steel joist with
concrete topping. The building
envelope includes burnished block units, precast concrete, brick veneer, glazed
curtain wall, punched window openings and metal panels.
Site utilities are all within 50 feet of the building structure.
Special features include controlling the amount of natural light
penetration and raised access flooring. Your
proposal will include a construction schedule, construction budget, a safe
production plan, a site orientation plan for site construction management for
material deliveries and SWPPP, a quality control plan and a project
organizational chart indicating all key staff required for this project.
Please keep in mind your owner is a very well respected architectural
firm with a critical eye for details and is also very budget minded.